Page Park Revitalization 

The Page Park Revitalization Project incorporates findings from the Master Plan Site Analysis and Community Survey, the Capital Improvement Plan, and the Strategic Action Plan and represents a wholesale re-imagining of this major city park.

Page Park 
649 King Street, Bristol, CT 06010 

Projected Timeline
*Please note project timelines are subject to change due to weather, inventory and supply chain availability, as well as scope and/or bid recipients. 

Phase I - Complete 

November 2024 - April 2026
- (4) Pickleball Courts with Lighting 
- Pickleball & Tennis Complex Pavilion/Shade Structure 
- (20) Car Parking Lot on DeWitt Page Park Road  
- (2) Car Reserved Parking Lot
- (50) Car Parking Lot at Disc Golf Course on DeWitt Drive
- Orchard Hill Road Trail Paving
Page Park Pond Retaining Wall Installation & Spillway Removal 
Westminster Road Trail Development
Pedestrian Walkways Sidewalks Paved


Additional sitework for Phase 1 includes: Electrical Improvements, Drainage and Irrigation, Erosion and Sediment Control, New Water Main System, New Storm Drain System, Sanitary Sewer System Relocation, and Landscaping.

Phase II* - Ongoing

April 2026 - December 2027
- Perry J. Spinelli Pavilion Access Road
- (60) Car Parking Lot and Round About Turn Around for Perry Pavilion and great Lawn Access
- Disc Golf Holes Modified and Replaced
Alternates:  
- Playground Installation
- Splash Pad Installation
- Great Lawn Construction
- Page Park Pond Fishing Piers

Future Phases*

Projected 2026 - 2027
Amenity Installation:
- (2) Basketball Courts with Bleachers and Lighting   
- (60) Car Parking Lot at King Street Entrance

Phase II - Project Updates

Blasting & Rock Removal 
May 2026 - Coming Soon
As Phase II gets underway, there will be rock removal and grading work happening for the Great Lawn area and Pavilion access road. During controlled blasts, neighbors may hear a muffled blast noise and/or may feel a slight vibration.
For any questions, please contact our office at [email protected] or 860-584-6160. 

Upgrade Your Play at Page Park 
May 2026 - Coming Soon!

Access to Orchard Hill Rd. Trail Impacted at Pavilion Entrance 
April 2026 - Access to the Orchard Hill Trail will be impacted during Phase II of construction at the Perry J. Spinelli Pavilion trail entrance. A roadway, parking lot, and turnaround area are being added adjacent to the Perry J. Spinelli Pavilion.  The "loop" will be impacted and the Pavilion Trail Entrance will be closed for extended periods of time. 

Posted Tree Removal
April 23, 2026 -  Superintendent Medeiros, Deputy City Tree Warden Doug Trillo, Weston & Sampson and Yield Industries conducted a site walk to identify and post trees scheduled to be removed. Per policy, the trees will be posted for 10 days to allow for public comment before being removed. Tree removal is required to accommodate the new access road and parking lot for Perry Spinelli Pavilion.   

Phase I - Progress, Development, and Completion 

Four New Pickleball Courts with Lighting
Status as of April 2026: Open / Lighting to be Installed and Programmed in late April 2026
Soft Opening held in October 2025 
-
The pickleball courts and tennis courts operate on a first-come, first-served basis for public use. BPRYCS offers 2-hour court rentals on a limited basis for $25.00 for 2-hours or $100.00 for a seasonal rental (April - October). 

Shade Structure and Shade Sail at the Pickleball & Tennis Complex 
Status as of April 2026: Completed / Available for Rent beginning April 2026 
-
A 28' x 36' open timber shade structure was erected adjacent to the tennis courts and features a split gable design. Community members can view the pickleball and tennis court complex as well as the baseball and softball fields from the pavilion. 

(20) Car Parking Lot on DeWitt Page Park Road 
Status as of April 2026: Open / Lighting to be Installed and Programmed
-
A (20) car parking lot is being constructed on Dewitt Page Park Road  between the tennis courts and  Page Pool. The Parking lot will serve the tennis and pickleball complex, as well as serve as overflow parking for the pool, sledding, softball, baseball, park events, and more.

(50) Car Parking Lot at the Disc Golf Course on DeWitt Drive
Status as of April 2026: Open / Lighting to be Installed and Programmed
-
A formally dedicated and paved parking lot is being constructed at the start of the Rockwell Park Disc Golf Course to replace the formal makeshift trailhead parking.

Orchard Hill Road Trail Development
Status as of April 2026: Open / Lighting to be Installed in Phase II / Ingraham Field Entrance Open to Pedestrians / Perry J. Spinelli Pavilion Entrance Closed Due to DeWitt Page Park Road construction*.
-
Orchard Road extends half a mile (0.5mi) and travels through the heart of Page Park; passing through the orchard field, Disc Golf Course, and old Page Park ski hill. The entire length of the trail has been paved for increased access to residents and community members. There are two main entrances to the trail:
- Between Ingraham Field the Disc Golf Course Parking Lot 
- Next to the Perry J. Spinelli Pavilion, just past the Page Park Pond*

*Access to the Orchard Hill Trail will be impacted during Phase II of construction at the Perry J. Spinelli Pavilion entrance. 

 Westminster Road Trail Development
Status as of April 2026: Open / Lighting to be installed in Phase II
-
Westminster Road was a vehicular roadway off of Oakland Street that extended into Page Park. The portion of Westminster Road beyond the Page Park entrance, located at the intersection of Westminster Road and Page Avenue is now available to pedestrians only and is no longer available to vehicle access. The trail adds 0.15 miles to the BPRYCS trail system and works to advance walking and biking connectivity by linking DeWitt Drive and Page Avenue. 

Page Park Pond Retaining Wall Installation & Spillway Removal 
Status as of April 2026: Completed & Operational
-
A retaining wall and spillway system are being constructed at Page Park Pond to help manage  a controlled flow of water into the drainage system and downflow areas. The new system will improve erosion and sediment control, reduce flooding, and prevent damage to the structure of the pond. 

Pedestrian Walkways and Sidewalks Paved
Status as of April 2026: Paving Complete / Lighting to be Installed in Phase II
-
A five foot paved multiuse pathway will extend along the roadways and amenities through Page Park. Increased access to dedicated pedestrian pathways improves safety, connectivity and accessibility. 

Request Updates 

Construction for Phase II of the project will began in April 2026. During this period, there may be temporary disruptions such as road and amenity closures. Construction is scheduled to take place Monday – Friday between the hours of 7:00am and 5:00pm.

To receive notifications regarding general project information, estimated construction timeline/schedule, the scope of Phase II, and/or any project updates, please provide your contact information below: 

Thank you!

If you have any questions or concerns during the construction process, please do not hesitate to contact us at [email protected] or call us at 860-584-6160. We greatly appreciate your support as we strive to deliver high-quality services and facilities that enhance the community's quality of life, meet the diverse needs of all citizens, and build a sustainable future.

Phase I - Project Updates

Dye Testing - Page Park Pond
August 28, 2025 - Page Park Pond was dye tested, which turns the water florescent green/yellow. The product used, Bright Dyes, is environmentally safe, biodegradable, and meets EPA standards for drinking water. It will disappear once it meets extreme dilution. For any questions, please contact our office at [email protected] or 860-584-6160. 

Soft Opening of Pickleball Courts and Reopening of Tennis Courts on 7/1
June 26, 2025 - We are excited to announce the soft opening of the pickleball courts at Page Park on July 1, 2025. Tennis courts at Page Park will also reopen to community members on July 1st. Learn More

Tennis Courts Closure
April 21, 2025 - The courts are slated to reopen at the beginning of June, pending weather, following the installation of accessible pathways. Alternative tennis courts are available at Peck Park (87 Daley St.). 

Dewitt Page Park Road Closure
December 7, 2024 - A portion of DeWitt Page Park Road spanning from the Tennis Court Parking Lot to the Page Pool Parking Lot will be closed  to accommodate construction in that portion of the park.

Westminster Road Closure
November 18, 2024 - A portion of Westminster Road spanning from the intersection at Page Ave to DeWitt Drive will be closed going forward as part of the revitalization. 

No Sledding at Page Park for the 2024/2025 Season
Effective Immediately, the sledding hills at Page Park are closed for the season to facilitate construction and protect the safety of park visitors. We appreciate your cooperation and apologize for the inconvenience!

What to Expect
November 2024 - Project timelines, construction hours, and activity locations. 

Notification of Construction Beginning
October 28, 2024 - After four years of community engagement and extensive design work, we are pleased to notify you that the first phase of the Page Park Revitalization project is beginning this fall.

Project Documents

Field Report 22
October 31, 2025

Field Report 21
October 14, 2025

Field Report 20
October 2, 2025

Field Report 19
September 18, 2025

Field Report 18
September 4, 2025

Field Report 17
August 21, 2025

Field Report 16
June 18, 2025

Field Report 15
June 5, 2025

Field Report 14
May 30, 2025

Field Report 13
May 12, 2025

Field Report 12
May 1, 2025

Field Report 11
April 17, 2025

Field Report 10
April 3, 2025

Field Report 9
March 12, 2025

Progress Report
February 2025

Field Report 8
February 27, 2025  

Field Report 7
February 13, 2025

Field Report 6
January 29, 2025

Field Report 5
January 9, 2025

Field Report 4
December 18, 2024

Field Report 3
December 5, 2024

Field Report 2
November 20, 2024

Field Report 1
November 2024

Future Phases
November 2024

Baseline Schedule
October 2024 

Phase I - English
October 2024

Phase 1 - Spanish
October 2024

Phase I Bid Awarded - Dayton Construction
September 2024

3D Renderings
August 2022

Groundbreaking - October 2024

On Wednesday, October 30, 2024 we broke ground on the Page Park Revitalization, which is the culminating work of over 6+ years of planning, engagement and design. The work will include a community great lawn, playground, splash park, 4 lighted pickleball courts, a pickleball and tennis complex pavilion and shade structure, nearly 200 additional parking spaces, pedestrian walkways and sidewalks, and restoration of the Page Park Pond and watercourse. Construction for phase 1 begins on Monday, November 4, 2024 and will take 18 months to complete. Informational letters were mailed to neighbors so they can learn more about the project and construction sequence.

Watch the Ground Breaking Video 

We Want Your Feedback! 

Please share your comments, questions, and input!

Message Sent!

Your message has been sent successfully, we appreciate your feedback!
Your Website Title
How to Share With Just Friends

How to share with just friends.

Posted by Facebook on Friday, December 5, 2014